Sl. No. | Project Title | PI / Co-PI | Sponsoring Agency | Duration |
1 | Fire Performance Assessment of Fire Door | Nawal Kishore Banjara | M/s Signum Fire Protection India Pvt. Ltd., PH. No. 6, KH No. 202/2, Village Waddhamna, Taluka, Hingna, Nagpur-440 023 | 01-2025 to 12-2025 |
2 | Fire Performance Assessment of Cememtecious Mortar Firestop | Nawal Kishore Banjara | M/s Stanvac Chemicals India Ltd., 551, Sector 37, Pace City-II, Gurgaon, Haryana | 01-2025 to 12-2025 |
3 | Fire Performance Assessment of Fire Door | Nawal Kishore Banjara | M/s NBCC India Ltd., NBCC Zonal Office, East Delhi Hub, Karkardooma Near GD, Goenka Public School, Behind Karkardooma Metro Station-110092 | 01-2025 to 12-2025 |
4 | Fire Performance Assessment of Fire Door | Sushil Kumar | M/s Window Tech India Pvt. Ltd., Plot No. 805, IMT Main Rd, Sector 69, Faridabad, Haryana-121004 | 01-2025 to 03-2025 |
5 | Fire Performance Assessment of V Panel Partition | Sushil Kumar | M/s Visaka Industries Ltd., Visaka Tower, 1-8-303/69/3, SP Road, Secunderabad, Telangana | 12-2024 to 03-2025 |
6 | Noncombustibility Evaluation of V Panel Sample | A. Aravind Kumar | M/s Visaka Industries Limited Survey No. 95,96, Gajala Puram Village, Madgula Pally Mandal, Nalgonda Dist.-508207 | 12-2024 to 11-2025 |
7 | Fire Performance Evaluation of treated and untreated samples of foam with Fabric | A. Aravind Kumar | M/s L&T Main Office, IICC (Yashobhoomi) Dwarka, Sector 25, New Delhi | 12-2024 to 11-2025 |
8 | Fire Performance Assessment of Fire Door | Nawal Kishor Banjara | M/s Supreme Metwood Private Ltd, 1031, Near Rajesh Dharamkanta, Dabua Pali Road, Village Bajri, Faridabad (har) - 121001 | 12-2024 to 02-2025 |
9 | Fire Performance Assessment of Fire Door | Nawal Kishor Banjara | M/s Sehgal Doors, B-133, Phase-1, Mayapuri, New Delhi | 12-2024 to 02-2025 |
10 | Fire Performance Assessment of Fire Dampers | Nawal Kishor Banjara | M/s G.S. Enterprises Plot No. 27/2/2, Nangli Sakrawati, Near Coca Cola Godwon, Nangli Sakrawati, New Delhi, South West Delhi, Delhi-110043 | 12-2024 to 11-2025 |
11 | Fire Performance Assessment of Fire Door | Nawal Kishor Banjara | M/s Navair International Pvt. Ltd., Plot No. 468, Barhi Industrial Area Sonipat | 12-2024 to 11-2025 |
12 | Fire Performance Assessment of Fire Door | Sushil Kumar | M/s Rock Miller All Tech India, Site No. 4, Assessment No. 34, Annapoorneshwari Nagae, Near Peenya 2nd Stage, Bangalore | 12-2024 to 02-2025 |
13 | Fire Performance Assessment of Fire Door | Nawal Kishore Banjara | M/s Swastik Doors LLP, B-207, Shreyas Industrial Estate, Near Western Express Highway, Jaycoach, Near Swastik Bar and Restaurant, Goregaon( E), Mumbai | 12-2024 to 02-2025 |
14 | Fire Performance Assessment of Fire Doors | Nawal Kishor Banjara | M/s GWS Engineers & Fabricators Pvt. Ltd, A-512, Mahape, MIDC, TTC, Thane Belapur Road Navi Mumbai-400701 | 12-2024 to 11-2025 |
15 | Fire Performance Assessment of Fire Door | Nawal Kishor Banjara | M/s Madhu Industries, #30, Pillaganahalli, Gottigere Post, Bannerghatta Main Road, Bangalore | 12-2024 to 11-2025 |
16 | Fire Performance Assessment of Fire Doors | Nawal Kishor Banjara | M/s Electrogroups India Khata No. 138, Khasra No. 31A, 31B, Tatiri, Aggarwal Mandi, Distt. Bagpat | 12-2024 to 11-2025 |
17 | Fire Performance Evaluation of Polyisocyanurate (PIR) Rigid Foam | A. Aravind Kumar | M/s ACE Builders & Engineers, Village- Samgoli, Derabassi, Punjab-140507 | 12-2024 to 11-2025 |
18 | Soil Sample testing collected from Glogi powerhouse landslide area | S. Ganesh Kumar | Uttarakhand Landslide Mitigation and Management Center (ULMMC), Govt. of Uttarakhand, 6th Floor, USDMA Building, IT Park, Sahastradhara Road, Dehradun | 12-2024 to 02-2025 |
19 | Fire Performance Evaluation of V Panel Samples | A. Aravind Kumar | M/s Visaka Industries Limited, Survey No. 95,96, Gajala Puram Village, Madgula Pally Mandal, Nalgonda Dist-508207 | 11-2024 to 10-2025 |
20 | Fire Performance Evaluation of Vermiculite Gypsum Based Fire Resistive Material | A. Aravind Kumar | M/s Newkem Product Corporation 3rd Floor, Harganga Mahal Dadar TT, Mumbai | 11-2024 to 10-2025 |
21 | M/s Visaka Industries Limited, Survey No. 95,96, Gajala Puram-Village Peddadevullapally-Post. Pincode-508207, Madugulappaly-Mandal. Near Miryalguda (Adjacent to Kukkadam Railway Station) Nalgonda District, Telangana State | Nawal Kishor Banjara | Fire Performance Assessment of V Panel Partitions | 11-2024 to 10-2025 |
22 | Fire Performance Assessment of Fire Door | Nawal Kishor Banjara | M/s MPS Techno Fab, Gat No. 107, Dawane Wasti Ambethan Road, Chakan | 10-2024 to 10-2025 |
23 | M/s The Executive Engineer, Health Project Division (Central), PWD (GNCTD) LNJP Hospital, New Delhi-110002 | Nawal Kishor Banjara | Fire Performance Assessment of Fire Door | 11-2024 to 10-2025 |
24 | M/s The Executive Engineer ( C ), HPD, (NH), Madipur, PWD, New Delhi-110063 | Nawal Kishor Banjara | Fire Performance Assessment of Fire Doors | 11-2024 to 10-2025 |
25 | Fire Performance Assessment of Fire Door | Nawal Kishor Banjara | M/s The Executive Engineer, HMD, (North), PWD, Dr. BSA Hospital Complex, Sector-06, Rohini, Delhi | 10-2024 to 09-2025 |
26 | Fire Performance Assessment of Fire Doors | Nawal Kishor Banjara | M/s DEC Industries Pvt. Ltd., 13-6-446/4, Gudimalkapur, Mehdipatnam | 10-2024 to 09-2025 |
27 | Fire Performance Assessment of Fire Door | Nawal Kishor Banjara | M/s Paulson Industries, Kokkappilly P.O. Thiruvankulam, Ernakulam, Kerala | 10-2024 to 09-2025 |
28 | Fire Performance Assessment of Fire Door | Nawal Kishor Banjara | M/s CMD Fabricators, Plot No. 295, Village-Chikhale, Post-Nehatoli, Tal-Wada, Dist-Palghar | 10-2024 to 09-2025 |
29 | Fire Performance Assessment of RCC Beams | Nawal Kishor Banjara | M/s National Council for Cement and Building Materials (NCCBM) Ballabgarh 34 Km Stone, Delhi-Mathura Road (NH-2), Ballabgarh | 10-2024 to 09-2025 |
30 | Fire Performance Assessment of Fibre Cement Board Partition | Nawal Kishor Banjara | M/s JollyBoard Ltd., J-6/J-7, Chikhalthana MIDC, Aurangabad | 10-2024 to 09-2025 |
31 | Fire Performance Assessment of Fir Dampers | Nawal Kishor Banjara | M/s Asawa Insulation Pvt. Ltd., 805, Cyber One, SP Marg, Sector-30, Vashi Navi Mumbai, Maharsahtra-400703 | 09-2024 to 08-2025 |
32 | Fire Performance Assessment of Fire Door | Nawal Kishor Banjara | M/s Kross Innovators Pvt. Ltd., 215, New India Industrial Estate, Mahakali Caves Road, Andheri East, Mumbai | 09-2024 to 08-2025 |
33 | Fire Performance Assessment of Firestop Barrier | Nawal Kishor Banjara | M/s Stanvac Chemicals India Ltd., 551, Sector 37, Pace City-II, Gurgaon, Haryana | 09-2024 to 08-2025 |
34 | Fire Performance Assessment of Protected Steel I-Beam | Nawal Kishor Banjara | M/s Sunanda Speciality Coating Pvt. Ltd., Sunshine Tower, 36th Floor, Senapati Bapat Marg, Lowerparel, Mumbai | 09-2024 to 08-2025 |
35 | Fire Performance Assessment of Fire Door | Nawal Kishor Banjara | M/s Doorwin Engineering 156, Sahitya Industrial Hub, Near Shiv Bhumi Estste, Kunjad to Gatrad Road, Village Bakarol (Bujarang, Taluko Daskrol, Ahmedabad | 09-2024 to 08-2025 |
36 | Fire Performance Assessment of Fire Door | Nawal Kishor Banjara | M/s Signature Interiors Pvt. Ltd., 23 Atrey Layout, Pratap Nagar, Nagpur | 09-2024 to 08-2025 |
37 | Fire Performance Evaluation of Underdeck Insulation Foam | A. Aravind Kumar | M/s L&T Main Office, IICC (Yashobhoomi) Dwarka, Sector 25, New Delhi | 09-2024 to 08-2025 |
38 | Fire Performance Evaluation of Acoustic Panel with PU foam and Non-Woven Fabric Liner | A. Aravind Kumar | M/s Lambda Buildtech Private Limited Plot 175 Bhakari, Faridabad | 08-2024 to 07-2025 |
39 | Fire Performance Evaluation of Sandwich PIR Continuous Line Panel | A. Aravind Kumar | M/s Suchi Foams Pvt. Ltd., Survey No. 1972, Sonvad Road, Village Khavad Taluka-kadi, Gujrat | 08-2024 to 07-2025 |
40 | Fire Performance Evaluation of Continuous Sandwich Puf Panels | A. Aravind Kumar | M/s Aqua Puf Panels & Heating System 138, Industrial Estate Phase III, Khonmoh Srinagar J&K | 08-2024 to 07-2025 |
41 | Surface Spread of Flame Evaluation of Sandwich PIR Continuous Line Panel | A. Aravind Kumar | M/s Suchi Foams Pvt. Ltd., Survey No.-1972, Sonvad Road, Village-Khavad, Taluka-kadi, Gujarat-382165 | 08-2024 to 07-2025 |
42 | Evaluation of thermal Conductivity ’K Value’ of Nitrile rubber Insulation of Aeroflex Make | Nagesh Babu Balam | M/s Unique Engineers Ltd., Service Apartment No: 927, Dwarka City Centre, Plot No-4, Sector-13, Dwarka, New Delhi-110078 | 08-2024 to 07-2025 |
43 | Fire performance assessment of elevator landing door | Nawal Kishor Banjara | M/s Shivshakti Elevator Componants Pvt. Ltd., Plot No. 2, HI Tech Park, Siddharth Nagar, Canal road Opp. Naveen Flourine Company, Bhestan, Surat | 07-2024 to 06-2025 |
44 | Fire Performance Assessment of CEPL Fire Doors | Nawal Kishor Banjara | M/s Centech Engineers Pvt. Ltd., Plot No. 68, Sector, IMT Faridabad | 07-2024 to 06-2025 |
45 | Fire Performance Assessment of Fire Doors | Nawal Kishor Banjara | M/s CS Components Pvt. Ltd., Plot No. 194, 195, GIDC Umbergaon Dist. Valsad, Gujrat | 07-2024 to 06-2025 |
46 | Fire Performance Assessment of PIR Partition | Nawal Kishor Banjara | M/s ACE Prefab (ACE Builders & Engineers) Village-Samgoli, Derabassi (Mohali) | 07-2024 to 06-2025 |
47 | Fire Performance Assessment of Fire Dampers | Nawal Kishor Banjara | M/s Syncro Industries Orient House, 3rd Floor, No.-647 Vijayashree Layout, Bannerghatha Road, Hulimavu, Banglore | 07-2024 to 06-2025 |
48 | Performance Evaluation of Sandwich Rigid Polyurethane (PIR) Insulated Panel | Rajesh Kumar | M/s Suchi Foams Pvt. Ltd, Survey No-1972, Sonvad Road, Village-Khavad, Taluka -kadi, Dist.-Mehsana | 07-2024 to 06-2025 |
49 | Fire Performance Evaluation of Polyurethane Rigid Foam Material | A. Aravind Kumar | M/s Kingspan Jindal Pvt. Ltd., Old Manesar Road, Narsinghpur, Gurugram | 06-2024 to 05-2025 |
50 | Fire Performance Assessment of Fire Rated Door | Nawal Kishor Banjara | M/s Navair International Pvt. Ltd., Plot No. 468, Barhi Industrial Area Sonipat | 06-2024 to 05-2025 |
51 | Fire Performance Assessment Of Fire Door | Nawal Kishor Banjara | M/s Tripti Engineering Services Pvt. Ltd., A/124, Baghajatin Pally, P.O.-Regent Estate, P.S. Patuli, Kolkata | 06-2024 to 05-2025 |
52 | Fire Performance Assessment of Polyurethane Sandwich Panel Partition | Nawal Kishor Banjara | M/s Kingspan Jindal Pvt. Ltd., Plot No.-129-135, Industrial Growth Centre, Sector-3, Pithampur, Dhar | 06-2024 to 05-2025 |
53 | Fire Performance Evaluation of Cross Linked Poly Ethylene (XLPE) Foam Material | A. Aravind Kumar | M/s Airmaster Indoplast Pvt. Ltd., 270 Anna Street Senthil Nagar Near Thirumullaivoyal Railway Station Chennai | 06-2024 to 05-2025 |
54 | Fire Performance Assessment Of Fire Door | Nawal Kishor Banjara | M/s SRS Engineers D-43, Phase-I, IDA, Jeedimetla, APIIC, Hyderabad, Medchal Malkajgiri | 06-2024 to 05-2025 |
55 | Fire Performance Assessment Of Fire Doors | Nawal Kishor Banjara | M/s Shakti Hormann Pvt. Limited, H. No. 2-67/1 (Survey No. 188,198) Gagillapur, Dundigal Municipality, Dundigal Gandimaisamma Mandal, Medchal (Malkajgiri) | 06-2024 to 05-2025 |
56 | Fire Performance Assessment Of Fire Door | Nawal Kishor Banjara | M/s R. S. Engineers & Services, Plot No. A-2/71, Site-IV, Industrial Area Sahibabad, District- Ghaziabad | 06-2024 to 05-2025 |
57 | Fire Extinguishing Performance Characterization and its evaluation studies of Advance Aegis Nanotech Fire Suppression Pad and Advance Aegis Nanotech Fire Suppression Wire | A.Arvind Kumar | Advance Safety Technology Pvt. Ltd., B/507, Great Eastern Summit, Plot No. 66, Sector 15, CBD Belapur, Navi Mumbai | 11-2023 to 04-2025 |
58 | Fire Performance Assessment Of Fire Door | Nawal Kishor Banjara | M/s NKG Infrastructure Ltd. IIM Amritsar Project Office, Manawala, Amritsar | 05-2024 to 04-2025 |
59 | Fire Performance Assessment Of Lift Landing Door | Nawal Kishor Banjara | M/s EC India, 53, Geason Colony, Galaxy Road, Ayanambakkam, Chennai | 05-2024 to 04-2025 |
60 | Fire Performance Assessment Of Fire Door | Nawal Kishor Banjara | M/s MORPH Plot No. 2,3 & 4 Malur Industrial Area, 4th Phase, Kolar District, Molur | 05-2024 to 04-2025 |
61 | Fire Performance Assessment Of Fire Door | Nawal Kishor Banjara | M/s Cleantech Engineering Pvt. Ltd. H.O. No. 204, B-65 Sector No. 1, Shanti Nagar Meera Road ( E) Distt. Thane | 05-2024 to 04-2025 |
62 | Fire Performance Assessment Of Fire Doors | Nawal Kishor Banjara | M/s Shakti Hormann Pvt. Limited, H. No. 2-67/1 (Survey No. 188,198) Gagillapur, Dundigal Municipality, Dundigal Gandimaisamma Mandal, Medchal (Malkajgiri) | 05-2024 to 04-2025 |
63 | Fire Performance Assessment Of Fire Door | Nawal Kishor Banjara | M/s Shreeji Woodcraft Pvt. Ltd., B-803, Western Edge II, Western Express Highway, Borivali( E) Mumbai | 05-2024 to 04-2025 |
64 | Fire Performance Assessment Of Fire Door | Nawal Kishor Banjara | M/s SI Surgi Engineering India Ltd., Eksara, P.O. Chamrail, P.S. Liluah, Howrah | 05-2024 to 04-2025 |
65 | Fire Performance Assessment of Sandwich Pir Wall Panel Partition | Nawal Kishor Banjara | M/s Suchi Foams Pvt. Ltd., Survey No. 1972, Sonvad Road, Village Khavad Taluka-kadi, Dist-Mehsana | 05-2024 to 04-2025 |
66 | Fire Performance Assessment Of Glazed Fire Door | Nawal Kishor Banjara | M/s ASES Security Pvt. Ltd., House, A, ASES, 2/69, Site-V Sahibabad Ind. Area, Ghaziabad | 05-2024 to 04-2025 |
67 | Performance Evaluation of Polyurethane Sandwich Panel | Rajesh Kumar | M/s. Kingspan jindal Pvt Ltd., Old Manesar Road, Narsinghpur, Gurugram | 05-2024 to 04-2025 |
68 | Performance Evaluation of Polyisocyanurate (PIR) Foams for thermal Insulation | Rajesh Kumar | M/s BNAL PREFABS Pvt. Ltd., Chandigarh | 04-2024 to 03-2025 |
69 | Fire Performance Evaluation Bamboo Samples | A. Aravind Kumar | M/s Guwahati Airport Project Adani Site Office, New Integrated Terminal Building, SOS Village Road, Opposite to Kiran Shree Grand LGBI Airport, Guwahati | 04-2024 to 03-2025 |
70 | Fire Performance Evaluation of Underdeck Insulation Material | A. Aravind Kumar | M/s India International Exhibition and Convention Centre Limited, Ministry of Textiles, 452A, Udyaog Bhawan, Maulana Azad Marg, Central Secretariat | 04-2024 to 03-2025 |
71 | Fire Performance Assessment of Fire Door | Nawal Kishor Banjara | M/s Pushpak Engineerings, No. 79 Karimsab Layout, Sringandhanagar, Near Konika Garments, Dodanna Industrial Area, Hegganahalli, urban, Karnataka | 04-2024 to 03-2025 |
72 | Reaction to Fire-Evaluation of Exosound-Acoustic Board | A. Aravind Kumar | M/s ALP Aeroflex India Private Limited Kharsa No. 82/9 & 83/9, Fazalpur, Mahrola, Opp. PG. College, Bilaspur Road, Distt. Udham Singh Nagar, Uttarakhand | 09-2024 to 03-2025 |
73 | Fire Performance Assessment Of Fire Doors | Nawal Kishor Banjara | M/s Halspan Limited, Regent House, Regent Centre, Linlithgow EH497HU, United Kingdom | 03-2024 to 02-2025 |
74 | Fire Performance Assessment Of Fire Doors | Nawal Kishor Banjara | M/s Vardhaman Corp, C/o Pratik Choudhary, Kakade Angan, A-11, Tanaji Nagar, Chinchwad, Pune | 03-2024 to 02-2025 |
75 | Fire Performance Assessment of Fire Door | Nawal Kishor Banjara | M/s KSP Engineering Survey No. 47/1/A, Vignaharta HSG Society, Dehugaon, Pune | 03-2024 to 02-2025 |
76 | Study on Impact and Bending Behaviour of Continuous Sandwich Panels | R. Siva Chidambaram | M/s Aqua Puf Panels & Heating System 138, Industrial Estate Phase III, Khonmoh Srinagar J&K | 08-2024 to 02-2025 |